Project Timeline
May-June 2005: Met with designer. Approved plans. Solicited a bid for cabinets. Things moving slowly.
July 2005: Cabinets almost ordered, just a few details to work out. Decided to hire a general contractor (see post titled "And so it grows", July 24, 2005.
Oct. 5 2005: Cabinets arrive at the warehouse.
Oct. 8 2005: Demolition.
Oct. 24 2005: Work on the kitchen begins (electrical, plumbing, etc.)
Dec. 9 2005: Rough work is finally completed and drywall is hung on the ceiling and walls. We spend the weekend priming and painting.
Dec. 12 2005: Cabinets are delivered to our home where they take up much space in the living/dining room and breakfast room.
Jan. 19 2006: Kitchen is fully functional. Cabinets, appliances, lighting and countertops installed.
July 2005: Cabinets almost ordered, just a few details to work out. Decided to hire a general contractor (see post titled "And so it grows", July 24, 2005.
Oct. 5 2005: Cabinets arrive at the warehouse.
Oct. 8 2005: Demolition.
Oct. 24 2005: Work on the kitchen begins (electrical, plumbing, etc.)
Dec. 9 2005: Rough work is finally completed and drywall is hung on the ceiling and walls. We spend the weekend priming and painting.
Dec. 12 2005: Cabinets are delivered to our home where they take up much space in the living/dining room and breakfast room.
Jan. 19 2006: Kitchen is fully functional. Cabinets, appliances, lighting and countertops installed.